I was able to screw in and glass down the first piece of flooring for the raised section this weekend. 9" tape was used to secure the piece to the sidewalls and cuddy sections:


plus some epoxy over the counter-sunk screw heads.
The top section of flooring and the middle sections were also screwed down and I applied some cabosil to the edges, in order to make the glass transition a little smoother...nothing too detailed here b/c we plan on duratek'ing the entire floor and that stuff looks like it makes everyone's work look a lil better:

we have a cut-out that will fit into the old step hole, next trip we'll glass that in and put a layer of 6" tape to the sides.


no pics but were also able to get the supports cab'd up for the batch floor hatch frame.